Contractors

Contractor management — pre-qual to permit

Four capabilities that compose into a real contractor program: pre-qualification, insurance tracking, training matrix, permit eligibility. Each one is a Composer block.

QEHS safety desk

Safety practitioners on staff


11 min read · 2 sections

The four capabilities

  • Pre-qualification — EMR, citation history, reference checks, site-specific questionnaire.
  • Insurance tracking — GL, WC, umbrella, additional-insured endorsement; expiry-aware.
  • Training matrix — person × skill, renewal cadence, evidence attached.
  • Permit eligibility — contractor company + individual person must both be cleared before a permit issues.

The permit gate is the forcing function

The single highest-leverage control is to gate permit issuance on the contractor-company record being green. Insurance expired? No permit. Site induction stale? No permit. The gate is a guard on the permit workflow, not a policy document.